Thursday, October 28, 2010

Thursday, 10/28/10

Today a ton of work got done. The brick repair guys came this morning and finished around lunch time. They worked way faster than I thought they would. Shown here is the kitchen window, which was resized. They filled in brick here, around the window that was in the shower, and above the crawl space door. They also added new mortar to anywhere that bricks were loose.
While they worked on that, Johnny and I worked inside. I started the day by putting in fiberglass insulation into the holes we riped in the walls, giving special attention to the bathroom. Working with fiberglass is terrible by the way. It gets everywhere and makes you very itchy, even with long sleeves on.

Johnny finished up the plumbing in the crawl space, which included fixing an old pipe that had come loose during our work. After that we both worked on putting down the kitchen floor as well as the closet floor. Besides for photos showing all of this, I am also posting one of how the green and big the grass has gotten. I will mow it as soon as it stops raining.






No comments:

Post a Comment